IT Exam,IT Certification,braindump,original questions, question pool,document, braindump, test questions, test question, dumps, test answers, cert24.com, preparation, pdf, certification questions, answers Certification, certification test, practice test, exam dumps, certification training, answers real questions
PRINCE2 PRINCE2 Foundation We believe in helping our customers achieve their goals. For this reason, we take great care while preparing our Questions and Answers , Core Administration. Our practice tests Administration are prepared with the help of highly professional people from the industry, so we benefit from their vast experience and knowledge.
QUESTION 1
Which of the following is not an objective of the process Initiating a Project?
A. It encourages the Project Board to take ownership of the project
B. It provides the benchmark for decision-making processes throughout the projects life
C. It confirms the existence of an acceptable Business Case justifying the project
D. It ensures that all project management authorities are appointed
Answer: D
QUESTION 2
Which of the following is NOT an objective of the process Controlling a Stage?
A. Ensure that quality is achieved as planned
B. Manage any deviations from Stage or Project Plans
C. Identifying the key products that the project will deliver
D. Manage on-time delivery of products within agreed tolerances
Answer: C
QUESTION 3
Whose responsibility is it to supply the Customer's quality expectations?
A. Project Manager
B. Senior User
C. Executive
D. Senior Supplier
Answer: B
QUESTION 4
The Project Board keeps a control of the project through:
1. Highlight Reports
2. Checkpoint Reports
3. Exception assessment
4. Quality Log
A. 1, 3 and 4 only
B. All of the above
C. land 3 only
D. 1, 2 and 3 only
Answer: C
QUESTION 5
Which of the following is a stable element within the Project Initiation Document?
A. Business Case
B. Project Plan
C. Project tolerance
D. Risk Log
Answer: C