IT Exam,IT Certification,braindump,original questions, question pool,document, braindump, test questions, test question, dumps, test answers, cert24.com, preparation, pdf, certification questions, answers Certification, certification test, practice test, exam dumps, certification training, answers real questions
PK0-003 Project+ (2009) We believe in helping our customers achieve their goals. For this reason, we take great care while preparing our Questions and Answers , Core Administration. Our practice tests Administration are prepared with the help of highly professional people from the industry, so we benefit from their vast experience and knowledge.
QUESTION 1
A project manager is responsible for meeting with the companys project review board to periodically evaluate the progress on a project. Which of the following is the role of the board?
A. To supply audit trail oversight
B. To ensure local standards compliance
C. To provide decision oversight
D. To communicate to stakeholders
Answer: C
QUESTION 2
Which of the following are components of an internal / external communication plan? (Select TWO).
A. Technology requirements
B. Communication budget
C. Distribution list
D. Stakeholders list
E. Communication frequency
Answer: CE
QUESTION 3
A project manager creates a detailed list of costs for each activity involved in the project and then uses the sum of the individual activities to create the budget. Which of the following cost estimating techniques was used?
A. Bottom-up
B. Expert judgment
C. Parametric
D. Top-down
Answer: A